I. Extension of Facilities - Underground
Rate Schedules and Policies Manual
|
|||
table of contents | back i1 | i2 | i3 |
|||
Extensions cont'd |
|||
Notwithstanding the foregoing, NB Power reserves the right to refuse an underground extension to its facilities for reasons of safety, environmental conditions or sound engineering practice. |
Conditions for |
||
Customers will supply, install, own and maintain their Underground Service Loop. A sufficient length of wire must be provided at the base of NB Power's supply device (e.g., padmounted transformer, pole) to allow connection to NB Power Facilities. |
Underground |
||
The optional underground facilities charge recovers the difference in construction costs between what NB Power normally supplies and what the Customer requests and is provided. All charges related to optional underground facilities are non-refundable. The optional underground facilities charge equals the total cost of the facilities less the NB Power investment for the equivalent standard overhead facilities. |
Optional |
||
table of contents | back i1 | i2 | i3 |
|||
disclaimer | NB Power - RSP 1 October 2000 |